Commissioned in 2006, Trtar Krtolin is the second wind farm built in Croatia. It was erected near the city of Sibenik using 14 Enercon E-48 wind turbines of 800 kW each.
wpd is now seeking to reduce the number of turbines to up to five, remaining faithful to the Enercon brand. The company plans to use Enercon E-160 machines with a capacity of 6 MW per unit and have the repowered wind farm reach 30 MW.
With more powerful turbines, the annual electricity production of the Trtar Krtolin site would go from about 30 GWh to some 55 GWh.
The project also includes installation of a 10-MW battery energy storage system (BESS). wpd used the Huawei Luna2000-2015 battery as an example of the potential technology.
wpd has four wind farms in Croatia, commissioned between 2006 and 2016, according to its website.
(renewablesnow.com, October 30, 2026)