The contract is covering design, execution, delivery, installation, testing, and commissioning, as well as the construction of necessary supporting infrastructure, news provider Ekapija reported last week.
The wind farm will have an installed capacity of 60 MW, consisting of ten wind turbines with a capacity of 6 MW each, and an estimated annual production of around 160 GWh.
Bidders have until October 12 to submit their offers, while tender documentation must be requested by October 1.
The project was previously developed with German capital, but Germany decided to terminate its participation in 2023 alongside three other infrastructure projects in the Serb Republic - worth a total of 105 million euro - as a sanction against the entity’s leadership.
The Serb Republic is one of two autonomous entities that form Bosnia and Herzegovina. The other one is the Federation.
(SeeNews, September 1, 2026)