These include:
- 59 solar plants with an installed capacity of 3 gigawatts (GW), representing an investment of around 2.1 billion euros
- 7 wind farms with a total capacity of 907 MW, amounting to 1.1 billion euros in investment
- 1 gas-fired cogeneration plant with an installed capacity of 495 MW, requiring 445.5 million euros in investment
The total capacity included in the plan is 4.4 GW, with an estimated total investment of 3.7 billion euros.
A significant segment of the plan comprises electricity storage systems:
- 77 integrated storage units, as part of existing or new power plants, with a total capacity of 1.4 GW and 3.5 GWh of storage
- 19 standalone storage units, with 637 MW capacity and 1.5 GWh storage
In total, the plan covers 96 energy storage units, with 2 GW total capacity and 5 GWh of storage, representing an estimated investment of nearly 2 billion euros.
Local initiatives and grid analyses
The annual plan also includes 56 energy facilities stemming from the energy plans of 7 municipalities. This comprises 52 MW of solar capacity and 61 storage units. The plan includes network and market analyses to ensure system stability and guide investments in new energy facilities.