One contract, valued at 310 million leks, covers the construction of a line linking the Koplik and Vukpalaj substations within 18 months. The other, worth 460 million leks, calls for extending the line to Tamare and building the substation within two years, according to the tender documents.
Bids for both tenders are due by September 1.
(See News, August 15, 2025)