company continues to expand its gas infrastructure in eastern Russia, the company said in a statement.
Construction of the facilities needed to start gas deliveries to China via the new route in the Primorsky region is nearing completion, the company said.
The Belogorsk-Khabarovsk gas pipeline is 98.5% complete and has been connected to the Power of Siberia and Sakhalin-Khabarovsk-Vladivostok pipelines, according to the statement.
Work on a second line along the Power of Siberia pipeline between the Chayanda gas field and Blagoveshchensk is also nearing completion, with commissioning underway.
Meanwhile, preparations to begin production at the Kharasavey gas field in the Arctic are in their final stages.
Gazprom said the investments are aimed at ensuring reliable gas supplies within Russia and meeting its export commitments.
Having lost much of its European gas market, Gazprom is seeking to offset the decline in exports by increasing supplies to Asia, particularly China.
(Anadolu Agency, November 25, 2026)